IndoSpace announced the launch of its Narasapura-II industrial and logistics park in Karnataka on 18 November, with an investment of ₹350 crore and roughly 1.05 million sq ft, according to a PTI report carrying the company’s statement. For manufacturers and warehouse tenants planning a move, the next useful document is the schedule showing which blocks can be handed over and when.

What space is being offered?

IndoSpace’s own park page places Narasapura-II in Alahalli village, about 4 km from NH 75, and lists a 40.9-acre site with 1.6 million sq ft of total chargeable area. It also says FMCG and third-party logistics businesses already occupy space there.

The area in the launch report and the chargeable area on the park page have different descriptions. A tenant comparing rent proposals needs to know which measurement includes the space it can actually use, which shared areas attract charges, and whether the quoted total covers the same development phase.

What did the earlier construction record show?

ICRA’s assessment dated 4 June 2026 described a six-block project with 1.02 million sq ft of leasable area. It recorded three blocks under construction at that time and 53% of project cost incurred as of 31 March. Its scheduled commercial-operations date was 1 April 2030, with construction expected in phases.

Those are dated financing and construction observations. The November launch may reflect later progress, and the developer’s current page claims existing occupants. The records reviewed do not provide a common, dated block schedule connecting those milestones. The difference between the three published area figures also needs a definition and scope reconciliation.

What should a tenant verify before moving?

A block handover should identify the usable floor area, the date access is available for fit-out, and the utilities and safety systems included in that handover. A manufacturer also needs to align equipment delivery and trial production with that date.

The park page advertises loading docks, fire-fighting systems and 12-metre clear height. A tenant can use those specifications to frame its technical inspection, then seek the applicable approvals and completion records for the particular block it is leasing.

The next evidence to watch is a dated occupancy and handover update that names the blocks, states their area basis and confirms the services ready for use. That would let customers plan a move against a building they can inspect.

AI-generated conceptual illustration of phased warehouse development.